Lynas ups Kalgoorlie capital costs budget to A$800m

The Kalgoorlie rare earths processing plant

The Kalgoorlie rare earths processing plant

24th April 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Rare earths miner Lynas has added another A$70-million to the final cost estimate of its delayed Kalgoorlie processing facility, with the full cost now set to come in at A$800-million.

This compares with the August 2023 budget of A$730-million and is now A$300-million more than the original price tag of A$500-million.

In its quarterly update on Tuesday, Lynas CEO Amanda Lacaze reported that commissioning and initial production activities were ongoing, following the first feed of material from Mt Weld in December.

She stated that the introduction of concentrate into the process had informed additional works and activities. This included enhanced electrical back-up systems following a major electricity outage in January, further testing of loading and unloading systems and additional testing of the flowsheet.

She also reported that the Mt Weld expansion project remained on schedule, with construction activities progressing as planned.

Structural, mechanical, piping and electrical works on Stage 1 were well advanced. Lacaze said the energisation and commissioning of the Stage 1 circuit would start over the next few months, and the Stage 1 circuit would initially be tied into the existing operation.

“A staged commissioning approach reduces commissioning risk and enables a step-up in production capacity in the latter part of this calendar year whilst the remainder of the plant is constructed.”

Construction of Stage 2 is also ramping up. All long lead time equipment are on site, including grinding mills and flotation cells. Concrete works are advancing and SMP works will start in late April.

Manwhile, Lynas reported “excellent” production rages, with total rare earth oxide production of 4 348 t, including neodymium and praseodymium production of 1 725 t.

“Our Malaysian team managed a very successful production ramp-up after the significant upgrade works which were completed in the previous quarter,” Lacaze said.

Edited by Creamer Media Reporter

Comments

Latest News

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.22 0.257s - 109pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: