PEA results show La Fortuna as ‘robust base’ for production growth
TSX-listed Minera Alamos on Thursday announced positive preliminary economic assessment (PEA) results for the La Fortuna gold project, in Durango, Mexico.
The PEA estimates average contained metal production of around 43 000 oz/y of gold, 220 000 oz/y of silver and 1 000 t/y of copper over a five-year mine life.
The initial “starter pit” comprises two-million tons of ore, grading 3.68 g/t gold, 20 g/t silver and 0.27% copper, to be processed at a rate of 1 100 t/d.
Using metals prices of $1 250/oz gold, $16/oz silver and $5 725/t copper, the PEA demonstrated an all-in sustaining cost (AISC) of $440/oz, an after-tax net present value (NPV) at 7.5% of $69.8-million and an internal rate of return (IRR) of 93%.
La Fortuna preproduction capital costs should amount to $26.9-million and, based on the economics in the PEA, the payback period should be about four months.
“With an after-tax IRR in excess of 90%, today’s excellent PEA results confirm that the La Fortuna project provides a robust base for the next phase of gold production in the company’s growth pipeline,” commented Minera Alamos CEO Darren Koningen.
He noted that the simplified gold recovery process outlined in the study represents a conservative starting point that is well suited to the initial project resource, which is based exclusively on previously drilled mineralisation.
“As our engineering work progresses, we continue to find opportunities to reduce the initial project capital requirements and improve overall project economics.
“Coupled with our strategic partnership with Osisko Gold Royalties that includes an option to provide a significant portion of the project capital requirements in return for a project royalty, these additional optimisations will greatly reduce the upfront funding requirements of this already low capital cost operation.”
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation