Bisie development on track

10th January 2019

By: Creamer Media Reporter

     

Font size: - +

The processing plant front-end crushing circuit at Alphamin Resources' Bisie tin mine, in the Democratic Republic of the Congo, has been successfully commissioned, on schedule.

This includes the primary crusher, two tertiary crushers and the screening buildings. Ore is now being fed through this circuit to create a stockpile with which the gravity circuit can be commissioned.
 
The process plant in its entirety is scheduled to be commissioned, on track with the original schedule, by the end of March.
 
Alphamin on Thursday also reported that the underground mine capital footprint had been completed at the end of December, two months ahead of schedule.

The run-of-mine ore production rate is being ramped up to about 1 000 t/d to achieve the targeted steady-state feed rate to the processing plant.
 
"It is envisaged that the processing plant should ramp up to its nameplate production capacity of tin concentrates from April to the end of June 2019," the company said.
 
“To have achieved such significant progress, to date, on time and within budget for a project of this scale, in a challenging environment, is a testament to the skill and dedication of our staff and contractors on the ground. We look forward to the commencement of tin concentrate production in the near future and will keep the market appraised of developments in this regard,” said Alphamin CEO Boris Kamstra.

To watch Creamer Media's latest video reports, click here
 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The login details you entered is incorrect. Please try and re-enter your username and password. If you continue having problems, please contact us at subscriptions@creamermedia.co.za for assistance.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

R/€ = 20.4540 Change: 0.0039
R/$ = 19.1112 Change: -0.0824
Au 2330.59 $/oz Change: 3.70
Pt 922.50 $/oz Change: -8.40