Caledonia achieves marginal increase in Q2 output

10th August 2018

By: Anine Kilian

Contributing Editor Online

     

Font size: - +

Toronto-headquartered Caledonia Mining’s 49%-owned Blanket mine, in Zimbabwe, produced 12 657 oz of gold in the second quarter ended June 30, marginally higher than that produced in the second quarter of 2017 and in line with expectations. 

“The second quarter was a difficult quarter for the business as production was adversely affected by lower-than-expected grade and tonnes mined.

“Grade for the quarter was 3.19 g/t. This is below target due to difficulties in accessing broken ground at AR South and higher-than-expected dilution at the Blanket orebody due to the introduction of long-hole stopping on the grounds of safety,” CEO Steve Curtis said in a statement on Thursday.

 Caledonia further reported an 86% year-on-year increase in adjusted earnings a share to 35.2c, mainly as a result of an increased export credit incentive (ECI) and higher deferred tax adjustments.

"Attributable profit for the quarter was substantially higher year-on-year at $2.6-million, boosted mainly by the increase in the ECI when compared to the same period in 2017.”

Cash generated by operating activities for the quarter was, however, lower than in previous periods due to substantial working capital movements.

Curtis stated that the negative working capital movements during the quarter had had an adverse effect on operating cash flow, with a net operating cash burn of $1.2-million during the quarter.

This, combined with capital investment of $5.6-million during the quarter, had a negative impact on the balance sheet with a net cash balance of $5.3-million at the end of the quarter. 

"Capital investment for the quarter was in line with our capital expenditure (capex) plan for 2018 at $5.6-million, most of which was incurred at central shaft, which has now reached a depth of 1 106 m. We expect capex to decline substantially after 2019 after we commission the central shaft as planned in 2020."

Cost performance for the quarter was, meanwhile, satisfactory, with on-mine and all-in sustaining costs (AISC) being well-contained.

On-mine costs of $717/oz for the quarter were 3% higher year-on-year, while AISC was flat at $856/oz.  

Caledonia reiterated that it remains on track to achieve production of 80 000 oz/y at the Blanket mine by 2021.  

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The login details you entered is incorrect. Please try and re-enter your username and password. If you continue having problems, please contact us at subscriptions@creamermedia.co.za for assistance.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

R/€ = 20.3993 Change: 0.1071
R/$ = 19.1612 Change: 0.1494
Au 2384.32 $/oz Change: 22.99
Pt 950.50 $/oz Change: -2.40