Cost blow-outs and delays confirmed at Oyu Tolgoi

3rd July 2020

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Mining major Rio Tinto on Friday confirmed a cost blow-out of between $1.3-billion and $1.8-billion at the Oyu Tolgoi copper project, in Mongolia, compared with the original $5.3-billion capital estimates.

Meanwhile, first sustainable production has been delayed by between 21 and 29 months compared with the 2016 feasibility study guidance.

The new cost estimate and development timeframe resulted from an updated feasibility study, which incorporated a new mine design for Panel 0 of the Hugo Dummett North underground mine at Oyu Tolgoi. The new design also confirms that the caving method of mining remains valid and that the underground schedule and costs remain within the ranges previously disclosed.

“This amended mine design is another positive step in the development of the underground mine which will unlock the most valuable part of Oyu Tolgoi. We remain focused on delivering the underground project safely and within the guidance ranges we have announced on both cost and schedule,” said Rio’s CEO for copper and diamonds, Arnaud Soirat.

The updated design retains two in-situ rock pillars on either side of Panel 0 for geotechnical stability. In the original mine design, these pillars were within the mining area.

As a consequence of leaving the pillars in place, the material contained in the pillars has been reclassified from ore reserves to mineral resources. It is expected that part of the material contained in these pillars will be recoverable at a later stage following additional studies, which are currently under way, Soirat said.

Ore handling infrastructure will be relocated to the pillars, located immediately north and south of the current Panel 0 boundaries. Panels 1 and 2 will now be initiated as independent panels or mine blocks.

Meanwhile, optimisation of mine designs for Panels 1 and 2 is ongoing and it is anticipated that this next phase of study may result in further movements in classifications of ore reserves and mineral resources.

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.141 0.181s - 93pq - 3rq
1:
1: United States
Subscribe Now
2: United States
2: