Cleaning|Concrete|Construction|Contractor|Copper|Design|Efficiency|Engineering|Environment|Excavators|Gas|Gold|Health|Installation|Mining|Platinum|PROJECT|Reinforcing|Risk Management|Safety|Service|Services|Steel|Surface|Sustainable|System|Systems|Technology|Trucks|Underground|Equipment|Shaft Sinking|Solutions|Environmental|Drilling|Operations
Cleaning|Concrete|Construction|Contractor|Copper|Design|Efficiency|Engineering|Environment|Excavators|Gas|Gold|Health|Installation|Mining|Platinum|PROJECT|Reinforcing|Risk Management|Safety|Service|Services|Steel|Surface|Sustainable|System|Systems|Technology|Trucks|Underground|Equipment|Shaft Sinking|Solutions|Environmental|Drilling|Operations
cleaning|concrete|construction|contractor|copper|design|efficiency|engineering|environment|Excavators|gas|gold|health|installation|mining|platinum|project|reinforcing|risk-management|safety|service|services|steel|surface|sustainable|system|systems|technology|trucks|underground|equipment|shaft-sinking|solutions|environmental|drilling|operations

Ivanplats to complete early-works construction at Platreef Shaft 2

SHAFT 2 Aerial view of the Shaft 2 box cut early works with the concrete hitch under construction

ROCK BOTTOM Workers at current shaft bottom (850 m) with cactus grab and kibble in the background

PLATREEF VIEW Aerial view of the Platreef project currently under development

DRILLINGS Workers drilling the next round to blast the bottom cut of the 850 m station

FRESH AIR The 850 m station and current bottom of Shaft 1 with ventilation column and kibble

INSPECTION Workers inspecting the 850 m station ventilation air flow

AT ANOTHER ANGLE Aerial view of Shaft 1 headgear and Shaft 2 box cut early works

MORE CONSTRUCTION Shaft 2 hitch construction under way

19th April 2019

By: Mc'Kyla Nortje

Journalist

     

Font size: - +

Ivanplats, the South African subsidiary of Ivanhoe Mines, is expected to complete early-works construction at Shaft 2 of the Platreef palladium/platinum/nickel/copper/gold/rhodium project, near Mokopane, in Limpopo, South Africa, in the second quarter, says Ivanplats VP and project director Gerick Mouton.

Mining contractor Murray & Roberts Cementation is the principal contractor for Shaft 2 and has employed the services of civil engineering company Concor Holdings as a subcontractor.

Mouton notes that Ivanplats will implement insights gained from Shaft 1 and current shaft sinking best practices while sinking Shaft 2. Various technical aspects relating to shaft sinking technology are being considered, including tracked excavators and tracked drill rigs for the mucking of rock and support drilling respectively.

“Engineering solutions that have been implemented to reduce or eliminate risk exposure at Shaft 1 will also be introduced while sinking Shaft 2.”

Meanwhile, Mouton points out that Ivanplats has completed the 450 m pumpstation and 750 m mining access station on Shaft 1. “The 850-m-level mining station is being developed and completion is also expected by mid-2019 – more than a month ahead of schedule. Moolmans is the principal contractor for Shaft 1 sinking and station development.

Shaft 1 is expected to reach its projected final depth of about 982 m, complete with the 950 m mining station, in early 2020.

Shaft 1 will become the primary ventilation shaft, while Shaft 2 will be the primary hoisting shaft to the Platreef mining zones.

Shaft 2 will have an internal diameter of 10 m and will be equipped with two 40 t rock-hoisting skips, which will have the largest hoisting capacity at any mine in Africa.

He says introducing unskilled individuals from the local community in Mokopane to shaft sinking operations and ensuring that the company transfers all the required skills to the new employees were some of the challenges.

“We now have more than 50% of our shaft sinking team from the surrounding Mokopane communities, and these employees are well-integrated into the sinking teams. Our safety and productivity performance is verification that this was highly successful,” adds Mouton.

Headgear

Ivanplats has completed the excavation of the box cut for the headgear as per the planned design down to a depth of 29 m, while construction of the ring beam and the tower hitch foundation is under way and scheduled for completion by midyear.

The concrete hitch, which is 33 m long, 29 m wide and 5 m in height, is currently being constructed. The foundation will support the 103-m-tall concrete headgear that will house the shaft’s permanent hoisting facilities and support the shaft collar. Mouton notes that the total foundation incorporates 10 600 t of concrete and 550 t of steel reinforcing.

A key advantage of using a concrete headgear, as opposed to a regular steel headgear, is that the concrete headgear allows for the installation of Koepe winder technology, reducing the surface footprint area of winding gear.

A Koepe winder is a system where the winding drum is replaced by a large wheel or sheave. Both cages are connected to the same rope, which passes around some 200 º of the sheave in a groove of friction material. It is often used for hoisting heavy loads from deep shafts and has the advantage that the large inertia of the ordinary winding drum is avoided.

The reinforced concrete headgear will house two Koepe winders. The rock winder will use a set of 40 t counterbalance skips and will have a hoisting capacity of six-million tonnes a year. The winders are best suited to high-production volumes and enhanced efficiency.

Meanwhile, the main winder will service a man cage with a capacity of more than 200 people in one lift, designed to allow for the transportation of large trackless equipment (50 t haul trucks and 17 t load-haul-dump machines) from surface to underground workings with minimal dismantling.

Safety Focus

Mouton explains that the health and safety of Ivanplat’s employees, contractors, visitors and other stakeholders involved in the Platreef project remain one of its core priorities.

“We have spent endless project hours in understanding the risks relating to our operation and how best we need to manage the risk exposure our employees face on a daily basis, especially with regard to shaft sinking.”

Following on this, the company has moved away from certain traditionally accepted shaft sinking practices to create a safer working environment and more resilient safety culture at the project. “Employees at Ivanplats are fully involved in these processes and, as a result, take ownership of the safe operating procedures,” Mouton emphasises.

He adds that the company’s leadership is committed to zero harm and has ensured continuous improvement in safe work methods since shaft sinking started at Ivanplats.

“We have challenged the conventional shaft sinking safety standards and have implemented safer and more productive methods of shaft sinking.”

Improvements that were introduced include bare enhanced ventilation and environmental management, shift clearance systems, new communication systems, removing people from shaft bottom during the lashing cycle, cleaning and mucking of the shaft bottom, as well as equipping the shaft services and safety nets around the stage platform.

In addition, the company uses the “hierarchy of control model” when conducting risk management reviews, with the primary focus on elimination, substitution and engineering solutions, rather than administrative and personnel protective equipment, as the latter are less effective and sustainable, Mouton explains.

Examples of risk reduction measures implemented at Shaft 1 – which have made a very positive impact on the overall safety culture and performance – include fully mechanised shaft lashing methods, with no employees at shaft bottom during cleaning when a cactus grab is used, and mechanical installation of safety nets between the sinking stage and shaft sidewalls.

Vehicles operating at the construction site are fitted with vehicle- and people- detection systems, while electronic gas-monitoring and shift clearance systems are employed.

Mouton concludes that entry examination and safe declaration processes are implemented as shaft sinking best practices.

Edited by Mia Breytenbach
Creamer Media Deputy Editor: Features

Comments

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.397 0.447s - 319pq - 2rq
Subscribe Now