Seabridge raises $150m from Sprott for KSM copper/gold project

Early-stage construction activities under way at the KSM camp.

Early-stage construction activities under way at the KSM camp.

12th May 2023

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Toronto- and New York-listed Seabridge Gold on Thursday announced a $150-million fundraising agreement with Sprott Resource Streaming and Royalty for its Kerr-Sulphurets-Mitchell (KSM) copper and gold project, in British Columbia.

Under the agreement, Sprott will be granted a 1.2% net smelter royalty on the KSM project.

“This new $150-million in financing, coupled with the $225-million we raised from Sprott and Ontario Teachers' Pension Plan last year, provide the capital we believe is needed to achieve substantially started status well before July 2026,” said chairperson and CEO Rudi Fronk.

Achieving the “substantially started” designation would ensure continuity of the KSM project’s approved environmental assessment certificate (EAC) for the life of the project.

The new financing also has the added advantage of cutting time from the construction schedule once a construction decision has been made, Fronk added.

KSM’s estimated low operating costs meant that the royalty would have a minimal impact on projected financial results.

In addition, the funding did not require shareholder dilution, Fronk said.

"Since our original investment last year, we continue to be impressed by the significant progress the Seabridge team is making at KSM. The quality of the engineering and early works is excellent, and their strong relationships with the local indigenous peoples are truly best-in-class. We are very pleased to expand our partnership with Seabridge and further accelerate KSM's development into a world-class mine,” commented Sprott managing partner Michael Harrison.

Yearly, the KSM operation will produce an average of 1.4-million ounces of gold, 251-million pounds of copper, 3.8-million ounces of silver and 2.1-million pounds of molybdenum.

A 2022 prefeasibility study estimates a capital requirement of $9.6-billion for the mine.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.085 0.116s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: